Project Management · Submittals

Free Submittal Schedule Template (Excel) - Construction Logs

Plan every submittal backwards from the day the material has to be on site, so long-lead items get submitted, approved, and ordered in time.

What's included

  • Planned submit and approval dates
  • Need-on-site dates
  • Lead time in weeks
  • Latest submit date calculated for you

Quick answer

Submittal Schedule Template: A forward plan of every submittal on a job, showing when each one must be submitted and approved so the material arrives by the day it is needed on site. Its format is Excel. It is for General Contractor, Project Manager, Project Engineer. It includes Planned submit and approval dates; Need-on-site dates; Lead time in weeks; Latest submit date calculated for you. It is a free download from Construction Logs.

Recommended

Prefer your phone?

Run live in Daily Build

A forward plan of every submittal on a job, showing when each one must be submitted and approved so the material arrives by the day it is needed on site.

DailyBuild is made by the Construction Logs team - your template, ready on your phone.

  • ■Fill it out from the field on any phone
  • ■Photos, signatures and timestamps attached
  • ■Automatic reports for owners and PMs
  • ■Free to start - no credit card

Quick summary

What it is
A forward plan of every submittal on a job, showing when each one must be submitted and approved so the material arrives by the day it is needed on site.
Best for
General Contractor, Project Manager, Project Engineer
Format
Excel
Price
Free ($0.00)
Pillar
Project Management

Template columns

Submittal #Spec SectionDescriptionSubcontractorPlanned Submit DateRequired Approval DateNeed-on-Site DateProcurement Lead Time (weeks)Review Allowance (days)Latest Submit DateStatus
00105 12 00Structural steel shop drawingsCarolina Steel Erectors2026-11-162026-12-142027-02-088142026-11-30 (formula)Submitted

The Latest Submit Date column is a formula: Need-on-Site Date minus lead time (weeks) minus the review allowance (days). If your planned submit date falls after the latest submit date, that item is already at risk and needs attention first.

Excel vs. Daily Build

ExcelDaily Build
PriceFreeFree to start
Mobile field entryNoYes
Photos & attachmentsNoYes
Automatic reportsNoYes
Works offlineYesYes

FAQ

What is a submittal schedule?

It is the plan for submittals, built before or early in the job. For each required submittal it sets the date it will be submitted, the date approval is needed, and the date the material has to be on site, working backwards from the construction schedule.

What is the difference between a submittal schedule and a submittal log?

The schedule is the plan, written before submittals go out. The log is the record, filled in as submittals are actually sent, returned, and approved. Most jobs need both: schedule first, then keep the log current against it.

How do I work out the latest submit date?

Start with the need-on-site date. Subtract the procurement lead time (fabrication and delivery) and then subtract the time you allow for review. The date left over is the last day you can submit and still hold the schedule. This template does that math for you in the Latest Submit Date column.

Which submittals belong on the schedule first?

The long-lead ones: structural steel, switchgear, rooftop units, elevators, custom doors and hardware. Anything with a lead time over six weeks should be scheduled at buyout, not when the subcontractor gets around to it.

Is this submittal schedule template free?

Yes. It is a free Excel download from Construction Logs, formulas included. Fill in your need-on-site dates and lead times and the latest submit dates calculate on their own.

  • RFI vs. Submittal: What's the Difference?

    Both go to the design team, but they serve very different purposes in the contract.

  • How Contractors Can Prevent Liquidated Damages with Better Delay Tracking

    A project can look profitable on paper until the schedule slips and the contract starts charging by the day. A few missed milestones can turn a healthy margin into a painful loss, especially when liquidated damages are written into the agreement.In construction contracts, liquidated damages are pre-agreed amounts the contractor may owe if the project is completed late. They are common on schools, multifamily projects, commercial buildings, public work, industrial jobs, and tenant improvements. T

  • Enhancing Contract Analysis with AI Technology

    Key Questions to Ask AI for Contract AnalysisWhen utilizing AI to analyze construction contracts, specific questions can guide the analysis effectively. Here are some example questions that can help in extracting critical information:1. What are the Payment Terms? Understanding the payment structure is essential. AI can quickly find and summarize clauses related to payment schedules, milestones, and penalties for late payments. 2. What Are the Warranty Terms? Warranty clauses protect y

Related templates